Engineering Practice

How to write a terminal automation system specification and RFQ

Write a TAS specification from processes, interfaces, failure cases and acceptance tests, so proposals from terminal automation vendors can be compared.

Topic
Engineering Practice
Updated
13 November 2026
Reading time
4 min
Sections
6
A specification document with ticked checklist rows beside a truck loading gantry and a PLC rack, showing the scope of a terminal automation RFQ.
Overview

A good terminal automation system (TAS) specification starts from the list of processes and documents the terminal must produce, then derives the field devices, interfaces, system availability and after-sales support from that list.

A specification written as a feature wish list invites proposals that tick every box and still fail on site. This guide follows the order an experienced owner's engineer uses for an RFQ (request for quotation) or a KAK (kerangka acuan kerja). If you need the basics first, the INTEGRA TAS product page shows the full gate-to-gate chain, and the article on TAS, TMS and TPS explains where each system's responsibility ends.

Start from processes and documents

Scope

Start from processes and documents

Write down what the terminal does and what paper it must produce before you write a single technical requirement. Everything else in the specification should trace back to that list.

For a fuel terminal the list usually covers receipt, storage, truck loading, gate control and reporting. For each process, name the trigger, the data it needs, the person who approves it and the document it closes with: tank ticket, delivery note, good issue, stock report. Requirements that do not trace to a process are either missing a process or are not needed.

  1. Process inventory

    List each process, its trigger, approver and closing document.

  2. Field survey

    Record every bay, meter, controller, gate and network cabinet with brand, model and condition.

  3. Interface list

    Define each data link, its owner, format and failure rule.

  4. Acceptance criteria

    Turn requirements into tests with pass and fail conditions.

  5. FAT, SAT and SIT plan

    Agree where and how each test runs, and who signs.

  6. Support and spares

    Specify response, backups, spares and the end of the support period.

The interface list is the core of the specification

Interfaces

The interface list is the core of the specification

Most TAS projects that run late are late at an interface, not inside the TAS. Each link between two systems has two owners, two vendors and two ideas of what a message means.

For every interface, write the direction of data, the trigger, the message content, the protocol, the owner on each side and what happens when the other side does not answer. The Citia Integrated TAS Portfolio shows a typical set: RFID and gate, a Siemens S7-300 PLC, WebAccess SCADA, INTEGRA TAS and TMS, and SAP with SIOD.

Ask bidders to say which side of each interface they will build, and which side they expect the owner or another vendor to supply.

ERP
Orders in, results and postings out
Distribution system
Shipment data, for example SIOD
TMS
Tank stock and tank tickets
Batch controllers
Presets in, batch results out
PLC / SCADA
Pumps, valves, permissives
Gate
RFID, barrier, weighbridge for LPG
Specify behaviour when something fails

Availability

Specify behaviour when something fails

A specification that only describes normal operation will get a system that only works in normal operation. Write the failure cases as requirements, each with a test.

Three cases cover most of the risk. When the ERP link is down, the terminal should keep loading against orders already received and queue the postings. If the TAS server fails, the specification should say whether a standby server takes over and what happens to a batch in progress. A network drop at one bay should let the running batch finish or stop safely, with no new batch starting.

Avoid asking for an availability percentage you cannot test. Ask instead for the switchover procedure, the recovery time you will witness at SAT, and the backup and restore procedure.

Acceptance tests: FAT, SAT and SIT

Testing

Acceptance tests: FAT, SAT and SIT

Acceptance tests are where the specification is proven, so the tests must be in the RFQ. A bidder prices what you ask it to prove.

IEC 62381:2024 sets out requirements and checklists for the factory acceptance test (FAT), an optional factory integration test (FIT), the site acceptance test (SAT) and the site integration test (SIT). Its purpose is to give owner, buyer and vendor one agreed basis for test scope and responsibilities. Use it as the frame and add terminal-specific cases: a full loading with a real truck per product, a gate-to-gate transaction posted to the ERP, and each failure case from the section above.

Test stages under IEC 62381:2024

  1. Factory

    FAT

    Software and panels tested against the specification with simulated signals.

  2. Factory, optional

    FIT

    Integration with other systems tested before shipment.

  3. Site

    SAT

    Installed system tested with real field devices.

  4. Site

    SIT

    End-to-end tests with ERP, TMS and other site systems.

Support, spares and security in the contract

Lifecycle

Support, spares and security in the contract

A TAS is used for many years after the project team leaves, so the specification must describe that period too. The contract model decides who answers the phone at night.

Citia's support records show what to write down. At Padalarang, faults in equipment outside the TAS contract were often seen as the TAS team's responsibility, so the boundary of scope had to be made explicit. At LPG Panjang, one standby technician covered office hours with on-call support outside them, and recurring communication loss between the weighbridge controller and the weighing house PC needed structured troubleshooting.

For security, IEC 62443-2-4:2023 lists the security program requirements an asset owner can ask of an industrial automation service provider during integration and maintenance. Ask bidders which of those requirements they already meet.

CriterionProject onlyProject + LTSAService model
Who owns faults after handoverOwner, after warrantyShared, as written in the LTSA scopeProvider, within the service terms
Changes such as new productsNew purchase order each timeOften included up to an agreed limitPart of the service
Backups and restore testsOwner's IT teamScheduled in the LTSAProvider's responsibility
Main riskKnowledge leaves with the project teamUnclear scope boundariesDependence on one provider
A checklist for the RFQ

Checklist

A checklist for the RFQ

  • Process and document list

    Every process with its trigger, approver and closing document.

  • Site survey data

    Brands, models and condition of all field devices and cabinets.

  • Interface list

    Owner, format, protocol and failure rule for each link.

  • Failure behaviour

    ERP down, server down and bay network loss, each with a test.

  • Tests and support

    FAT, SAT and SIT scope, spares list, response times and restore drills.

  • Security practice

    Remote access rules and the provider's position against IEC 62443-2-4.

When proposals arrive, score them on how well they answer the interface list and the failure cases, not on the length of the feature table. Ask each bidder to name a reference site where the same interfaces run today, and talk to the people who maintain it.

Terms used in this article

RFQ
Request for quotation, the document that asks vendors for priced proposals.
KAK
Kerangka acuan kerja, the Indonesian term of reference for a project.
FAT
Factory acceptance test, run before shipment with simulated signals.
SAT
Site acceptance test, run after installation with real devices.
SIT
Site integration test, end-to-end with other site systems.
LTSA
Long-term service agreement for maintenance and support after handover.
Interface list
Table of every data link between systems, with owners and rules.

Frequently asked questions

What should a TAS RFQ contain at minimum?

A TAS RFQ should at minimum contain the process and document list, site survey data, the interface list, failure behaviour, acceptance tests and the support scope. Without the interface list and tests, proposals cannot be compared fairly.

How do you evaluate terminal automation system vendors?

Evaluate vendors on how they answer your interfaces and failure cases, and check a reference site that runs the same interfaces. A long feature list matters less than a clear plan for integration, testing and support.

What is the difference between FAT and SAT?

FAT is run at the vendor's facility before shipment with simulated signals; SAT is run on site after installation with real devices. IEC 62381:2024 also defines SIT for end-to-end tests with other site systems.

Why should spare parts and backups be in the specification?

Spare parts and backups must be in the specification because they decide how fast the terminal recovers from a fault. If they are added after award, they are priced without competition and often left out.

Which standard covers the security duties of an automation service provider?

IEC 62443-2-4:2023 covers the security program requirements for service providers that integrate and maintain industrial automation and control systems. It belongs to the ISA/IEC 62443 series.

Sources and further reading

  1. IEC 62381:2024 Automation systems in the process industry: FAT, SAT and SIT (opens in a new tab)International Electrotechnical Commission (IEC) · webstore.iec.ch · 2024
  2. IEC 62443-2-4:2023 Security program requirements for IACS service providers (opens in a new tab)International Electrotechnical Commission (IEC) · webstore.iec.ch · 2023
  3. ISA/IEC 62443 Series of Standards (opens in a new tab)International Society of Automation (ISA) · isa.org
  4. Padalarang TAS lifecycle support (opens in a new tab)PT Citia Engineering Indonesia · citia-engineering.com · 2026
  5. LTSA for LPG Panjang (opens in a new tab)PT Citia Engineering Indonesia · citia-engineering.com · 2022
  6. Integrated TAS Portfolio (opens in a new tab)PT Citia Engineering Indonesia · citia-engineering.com

Next step

Prepare the technical discussion for your facility.

Bring the equipment list, diagrams and symptoms you have. The Citia team helps map the next step.