2023Finished
KF flowmeter
This project is the supply and installation of a metering system for the Kimia Farma boiler facility.

- Year
- 2023
- Location
- Bandung, Jawa Barat
- Status
- Finished
- Work types
- SCADA, Instrumentation, Sensor, PLC
- Updated
In outline, the work covers:
1) Supply of main equipment (flow metering system)
The vendor must supply several types of flow meter:
Water flowmeter (6 units)
Diesel (Solar) flowmeter (3 units)
CNG flowmeter (3 units)
With these technical specifications:
Brand: Siemens / Emerson / Endress+Hauser
Type: Digital/Magnetic Flowmeter
Accuracy: ±0.5% Full Scale
Material: Stainless Steel 316L
Flow rate range to suit each fluid
2) Monitoring and integration system
The work is not only installing flow meters. It also includes:
Integration to the existing PLC
Development of the PLC program
Development of SCADA-based monitoring software
Supply of a PC set, printer and local display
The aim is that all fluid consumption data can be:
Shown in real time
Recorded
Monitored from the control room
3) Mechanical and electrical work
The vendor must carry out:
Pipe modification (cutting, welding, grinding)
Flange and mounting installation
Cable pulling, and installation of cable tray and conduit
Installation of the flow meters on the existing pipe line
Power and signal connection to the PLC
All mechanical work is done by certified welders.
4) Calibration, testing and commissioning
This includes:
Internal calibration of the flow meters
Accredited metrology calibration (KAN)
Program testing
Commissioning until the equipment is fully functional
5) Documentation and warranty
The vendor must provide:
Certificate of Origin
Operating Manual
QC Approval
Boiler operator training
After-sales warranty and spare parts availability
A maintenance period of at least 1 year
From site
Field photos.