2024Finished
HPM and Rolls-Royce: data center generator sets JKT02 and JKT05
Generator installation, QA/QC inspection, testing and commissioning documentation. This document is a set of technical records prepared for the JKT02 Project and the JKT05 Project.

- Year
- 2024
- Location
- Jakarta, Jawa Barat
- Status
- Finished
- Work types
- Panel, Other
- Updated
Generator installation, QA/QC inspection, testing and commissioning documentation. This document is a set of technical records prepared for the JKT02 Project and the JKT05 Project.
It covers every stage of work: installation, Quality Assurance and Quality Control (QA/QC), pre-commissioning, testing, commissioning and operational readiness for the generator system and all its supporting equipment. The purpose of the document is to give a complete, documented record of all verification, inspection, testing and validation of the system.
This confirms that each installed item meets the design requirements, technical specifications, safety standards, project quality standards and manufacturer recommendations before it is handed over for operation.
Read the full record
The scope includes inspection of the mechanical, electrical, instrumentation and control system installation, installation quality checks (QA/QC Inspection), foundation dimension verification (Plinth Dimension Inspection), a system readiness check before operation (Vendor Pre Start-Up Inspection), the Initial Start-Up, and a series of tests and commissioning of all main and supporting generator systems.
Testing followed the procedures and test scripts prepared to make sure each system works according to the design philosophy and the operational needs of the facility.
The tests include the Generator Load Test, Fuel Polishing System Test, Fuel System Test, Fuel Heater Panel Functional Test, Generator Alarm System Test, and the Water Mist Panel and Fire Protection System Functional Test.
Each stage used functional inspection, simulation of normal and abnormal operating conditions, verification of alarms and interlocks, testing of protection devices, recording of operating parameters, and evaluation of results against the defined Acceptance Criteria.
All results are documented as inspection reports, verification checklists, measurement data, test results, visual documentation, and completion records where nonconformities were found during the work. This documentation is the evidence that all systems went through full verification and validation to the project quality standard.
The document is part of the Project Completion Documentation and the Commissioning Dossier. It is the basis for Performance Verification, the Site Acceptance Test (SAT), Project Handover and the readiness of the facility to enter operation.
Besides serving as the project handover document, it is a technical reference for operation, maintenance, periodic inspection and performance evaluation of the system during the operating life of the facility on site.