2020Finished

ABB Keppel

The ABB Keppel project supported the installation, integration and testing of electrical and automation systems at an industrial facility.

Technician wiring a control cabinet at Keppel data center
Keppel data center: Technician wiring a control cabinet
Year
2020
Location
Bogor, Jawa Barat
Status
Finished
Work types
Panel, Other
Updated

Overview

The ABB Keppel project supported the installation, integration and commissioning of electrical and automation systems. The work covered panel installation, cable termination, system configuration, function testing, troubleshooting and system verification, so that all equipment can operate to the technical specification and safety standards.

Challenges

  • Integrating the system with existing equipment.

  • Carrying out the work on the project schedule.

  • Making sure all connections and system functions work before commissioning.

Solutions

  • Inspected the installation and verified the wiring thoroughly.

  • Ran continuity tests, I/O tests and functional tests before the system went into operation.

  • Troubleshot and corrected faults until the whole system operated as designed.

Lessons learned

  • A thorough check of the installation reduces the chance of faults during commissioning.

  • Good coordination between teams speeds up completion of the work.

  • Documenting test results and system configuration makes maintenance and future development easier.