2020Finished
ABB Keppel
The ABB Keppel project supported the installation, integration and testing of electrical and automation systems at an industrial facility.

- Year
- 2020
- Location
- Bogor, Jawa Barat
- Status
- Finished
- Work types
- Panel, Other
- Updated
Overview
The ABB Keppel project supported the installation, integration and commissioning of electrical and automation systems. The work covered panel installation, cable termination, system configuration, function testing, troubleshooting and system verification, so that all equipment can operate to the technical specification and safety standards.
Challenges
Integrating the system with existing equipment.
Carrying out the work on the project schedule.
Making sure all connections and system functions work before commissioning.
Solutions
Inspected the installation and verified the wiring thoroughly.
Ran continuity tests, I/O tests and functional tests before the system went into operation.
Troubleshot and corrected faults until the whole system operated as designed.
Lessons learned
A thorough check of the installation reduces the chance of faults during commissioning.
Good coordination between teams speeds up completion of the work.
Documenting test results and system configuration makes maintenance and future development easier.
A similar need?
Tell us about your facility.
Name the equipment you run and what has to change. We reply with the questions we would ask on site.