# Fuel terminal automation in Indonesia: how it works and how to prepare an implementation

How a fuel terminal automation system runs a TBBM day to day, which components sit in each layer, which Indonesian rules shape the design, and what to prepare before an implementation starts.

| Field | Value |
| --- | --- |
| Topic | Terminal Operations |
| Author | Citia Engineering team |
| Published | 2026-11-18 |
| Updated | 2026-11-18 |

## Key takeaways

- A fuel terminal automation system runs receipt, storage and truck loading at a TBBM, with every quantity taken straight from the measuring instruments, from the order in SAP to the delivery note and the stock posting.
- Its components sit in four layers (field, control, application and enterprise), and a failure in an upper layer must never switch off a safety function in a lower one.
- In Indonesia, meters and tanks used for custody transfer need tera ulang under Permendag 24/2024, and fuel trading licence holders must digitalise their storage facilities and link them to the BPH Migas information system (Peraturan BPH Migas 9/2020, Pasal 7).
- The preparation that decides an implementation is data: the device list with protocols, the tera status of each instrument, the SAP interface list and a bay-by-bay cutover plan.

A fuel terminal automation system is the combination of field instruments, controllers and software that runs receipt, storage and truck loading at a fuel terminal (TBBM), and records every quantity directly from the measuring devices. In Indonesia it usually means a terminal automation system (TAS) for the loading side and a tank management system (TMS) for the tank side, connected to SAP. For the basic definition, see [what a TAS is](https://citia-engineering.com/en/knowledge/what-is-a-terminal-automation-system); for the terminal itself, see [what a TBBM is](https://citia-engineering.com/en/knowledge/tbbm-fuel-terminal).

This guide is written for people who will run, buy or support such a system at an Indonesian terminal. It follows one loading cycle from start to finish, maps the components layer by layer, lists the regulations that shape the design, and ends with the preparation work that most often decides whether an implementation goes smoothly. The examples come from Citia's projects at Pertamina terminals.

## How one loading cycle runs

A fuel terminal automation system works by checking each step of a truck's visit against the step before it, so that no truck loads without a valid order and no litre leaves without a record. The cycle starts in SAP, where the sales order or shipment becomes a loading order that the TAS can read. At the gate, the driver taps an RFID or NFC card; the TAS checks that the truck, its driver and the order belong together, and the gate opens only if they do.

The truck then waits in a queue until the TAS assigns a bay. At the bay the driver connects the earth clamp and the loading arm. The PLC confirms the permissives, such as earth, arm position and overfill sensor, and the batch controller receives the preset volume for each compartment. Loading starts from the bay, and the meter and batch controller stop it at the preset. The [batch controller](https://citia-engineering.com/en/knowledge/batch-controller) and [filling shed](https://citia-engineering.com/en/knowledge/filling-shed-loading-rack) articles explain the bay equipment in detail.

When loading ends, the batch controller sends the gross and net volumes back to the TAS. The compartments are sealed, physically or with a [digital seal](https://citia-engineering.com/en/products/fuel-digital-seal), the TAS prints the delivery note, and the truck leaves through the exit gate, where its card closes the visit. The TAS then posts the result to SAP. If any step is skipped, the next one refuses to start, and that refusal is what makes the record trustworthy.

- Order from SAP: The shipment or sales order becomes a loading order in the TAS.
- Gate-in: Card tap; the TAS checks truck, driver and order before the barrier opens.
- Queue and bay: The TAS assigns a bay that has the right product and is free.
- Permissives: Earth, arm position and overfill sensor confirmed by the PLC.
- Preset and load: The batch controller loads each compartment to its preset.
- Seal and documents: Compartments are sealed and the delivery note is printed.
- Gate-out and posting: The visit closes at the exit and the result is posted to SAP.

## Components, layer by layer

The components of a fuel terminal automation system fall into four layers, and the line between them decides what keeps working when something fails. The field layer measures and acts. The control layer makes the fast decisions that must not wait for a network. The application layer holds the transaction and stock records. The enterprise layer is where orders start and where stock and sales are booked.

A useful test for any design is to unplug the layer above and ask what happens. If the TAS server stops, a bay that has already received its preset should finish the batch safely and keep the result until the server returns. If SAP is unreachable, the terminal should still be able to run on orders already downloaded. The [TAS architecture](https://citia-engineering.com/en/knowledge/tas-architecture) article goes deeper into these failure modes, and [integrated TAS portfolio](https://citia-engineering.com/en/products/integrated-tas-portfolio) shows how Citia packages the layers.

- Field layer: Flow meters, control valves, ATGs, temperature and pressure transmitters, RFID readers, grounding units, overfill sensors, pumps and motor-operated valves.
- Control layer: PLCs, batch controllers, the gate controller and, where required, a separate safety system for ESD.
- Application layer: TAS for orders and loading, TMS for tank stock, SCADA for operators, plus the database and report server.
- Enterprise layer: SAP or another ERP for orders, stock postings and billing, plus regulator reporting.

## The tank side: receipt, storage and stock

On the tank side, automation turns gauge readings into a stock figure that the terminal, the owner and the regulator can all use. Each tank has an automatic tank gauge (ATG) that reports level and usually temperature. The TMS converts level into volume through the tank's calibration table, subtracts free water and applies the volume correction factor to reach the volume at the reference temperature. The [tank management system](https://citia-engineering.com/en/knowledge/tank-management-system-explained) article explains each step.

Receipts by pipeline or ship are handled the same way: the TMS takes the opening and closing gauges, issues the tank ticket and posts the physical inventory to SAP. [INTEGRA TMS](https://citia-engineering.com/en/products/tank-management-system) reads ATG data through a gateway into an SQL database, keeps history and posts to SAP over the intranet. Those stock figures also feed regulator reporting. Peraturan BPH Migas 9/2020 on operational fuel reserves requires each fuel trading licence holder to report, per storage facility, at least the average daily distribution, the daily volume of operational reserves and the location and capacity of the facility (Pasal 8). The report is a daily record submitted every month, no later than the 20th of the following month, through an online channel integrated with the BPH Migas information system (Pasal 9).

The quality of those reports depends on the gauges and the calibration tables underneath them, which is the subject of the article on [tank gauging accuracy and regulation](https://citia-engineering.com/en/knowledge/tank-gauging-accuracy-regulation). Upgrades on the tank side can usually run while the terminal operates; the [Cikampek tank monitoring upgrade](https://citia-engineering.com/en/projects/cikampek-tank-monitoring) was done in phases, with wiring and communication checks, loop checks, I/O tests and functional tests before each part went live.

## Rules that shape the design in Indonesia

Several Indonesian regulations and international standards decide what the system must measure, record and report, so they belong in the specification from the first draft. Legal metrology sets which instruments need tera and how often. BPH Migas sets what stock data must be digitalised and reported. International standards cover metering accuracy, hazardous areas, static electricity and cybersecurity.

The table lists the ones that most often change a design decision. Intervals come from Lampiran I of Permendag 24/2024; confirm the instruments at your site with the metrology authority, because the regulation separates instruments used in trade from those used only for company control.

The trucks are measuring instruments too. Lampiran I lists fuel tank trucks (tangki ukur mobil BBM) with a 2-year interval, and Pasal 18 lets an owner apply for exemption from tera ulang when a truck is used only as a means of transport. Which route a fleet follows changes what the TAS should record: the meter result alone, or the meter result checked against the certified capacity of each compartment.

- UU 2/1981 and Permendag 24/2024: Tera and tera ulang of meters, tanks and level gauges used in trade; for example 1 year for PD and turbine meters, 2 years for automatic level gauges, 6 years for vertical cylindrical tanks | Keep a tera calendar in the system and never add devices to a tera-marked instrument without asking the metrology authority
- Peraturan BPH Migas 9/2020: Digitalisation of storage facilities linked to the BPH Migas information system; daily records reported monthly | Plan a reporting interface fed directly from the TMS, so nobody re-types a spreadsheet each month
- OIML R 117-1:2019: Accuracy of dynamic measuring systems; most liquid fuel systems are class 0.5 | The TAS stores the measured result; accuracy comes from the meter and batch controller
- IEC 60079 series and NFPA 77: Equipment in hazardous areas; control of static electricity during loading | Ex-certified field devices and a grounding permissive in every bay
- IEC 62443 series: Security of industrial automation and control systems | Network zones that separate SAP from the TAS and the PLCs, plus controlled remote access for support

## Preparing an implementation

Most implementation delays come from missing data and unclear ownership, rarely from the software itself, so preparation starts months before any equipment arrives. The phases below are typical for a TAS or TMS project at a running terminal; their length depends on the size of the site and on how much of the existing equipment is kept.

Start with a site survey that lists every device the system will talk to: meters, batch controllers, ATGs, RFID readers, PLCs, gates and printers, each with make, model, firmware and protocol. Add the tera status of every meter and tank, because a device that is close to its due date may be better replaced during the project than after it. Then write the interface list with the SAP team: which messages carry orders, which carry results, who owns each field and what happens when a message fails.

The functional design specification (FDS) turns that list into behaviour: what the TAS does at each step, what the PLC does without the TAS, and how operators recover from faults. Factory acceptance tests (FAT) prove the software against the FDS before it reaches site, and site and integration tests (SAT and SIT) prove it with the real devices. IEC 62381 describes these tests for process automation. The [TAS specification and RFQ](https://citia-engineering.com/en/knowledge/tas-specification-rfq) article lists what the specification should contain, and [choosing a system integrator](https://citia-engineering.com/en/knowledge/choosing-automation-system-integrator) covers how to compare contractors.

## Typical phases of a TAS or TMS implementation

- Phase 1: Survey and data. Device list with protocols, tera status, drawings and the SAP interface list.
- Phase 2: Design. FDS, network zones, cutover strategy and test procedures.
- Phase 3: FAT. Software and panels tested against the FDS before shipment.
- Phase 4: Installation. Field wiring, panels, servers and network, done around operations.
- Phase 5: SAT and SIT. Loop checks, device tests and end-to-end transactions with SAP.
- Phase 6: Cutover and support. Bay-by-bay switchover, then a long-term service agreement.

## Mistakes we see most often

The mistakes that hurt most are decided early and discovered late. Each one below has a simple preventive step that costs little if done during design.

- Safety logic inside the TAS. Grounding and overfill permissives belong in the PLC or batch controller, so loading stops safely even when the server is down. See [static grounding](https://citia-engineering.com/en/knowledge/static-grounding-loading).
- No owner for master data. Product codes, compartment sizes and customer data change over time. When Biosolar B50 replaced B40, the [B50 product update](https://citia-engineering.com/en/projects/b50-product-update-padalarang-fuel-terminal) at Padalarang needed product and material codes reconfigured in the application and test transactions before operation.
- Integration left to the end. SAP messages tested only at SIT leave no time to fix field mapping. Test them with sample data during design.
- Flat networks. An office network that reaches PLCs directly is a cybersecurity and reliability risk; the [OT cybersecurity](https://citia-engineering.com/en/knowledge/ot-cybersecurity-terminals) article explains zoning.
- No plan after go-live. Spare parts, backups and on-call support should be agreed before handover, as described in [long-term service agreements](https://citia-engineering.com/en/knowledge/ltsa-control-system-maintenance).

Test the failure cases too: During SAT, pull the network cable from the TAS server in the middle of a loading. The bay should finish the batch, keep the result and hand it over when the link returns. If it does not, fix it before go-live, because the same thing will happen on a busy day.

## What changes for the people at the terminal

Automation moves work from typing and checking paper to watching exceptions, so roles change more than headcount. Before automation, a gate officer copies the order number, a bay operator writes the meter reading and an administrator reconciles both at the end of the shift. After automation, the TAS links those records by itself, and people spend their time on the cases the system refuses: an expired card, a compartment that did not reach its preset, an order that SAP has not released.

That shift needs preparation of its own. Operators need training on the new screens and, more importantly, on the fallback procedure when a device or the network fails. Supervisors need to know which reports to read each morning. The instrument team needs spare parts and a clear line to the contractor for faults it cannot fix. Plan the training before SAT, so the people who will run the system take part in testing it.

## After go-live

A terminal automation system needs planned support for its whole life, because devices age, products change and integrations drift. At the [Jambi fuel terminal](https://citia-engineering.com/en/projects/jambi-terminal-automation), Citia's TAS ties shipment, gate-in, the filling shed and gate-out to SAP, SIOD, RFID, flow meters, the meter user interface, PLCs and pump control, and lifecycle support covers monitoring, troubleshooting, maintenance and development. At [Padalarang](https://citia-engineering.com/en/projects/padalarang-tas-lifecycle), the long-term service agreement covers the FDM and FD-Flow applications, the TAS server, the gate interface PC, the NFC readers and the fibre links, with a monthly visit and a database backup on each visit.

For a terminal planning its first system or replacing an old one, the [INTEGRA TAS](https://citia-engineering.com/en/products/terminal-automation-system) page lists the functions Citia delivers, and [INTEGRA Access](https://citia-engineering.com/en/products/access-control) and the [batch controller interface](https://citia-engineering.com/en/products/batch-controller-interface) cover the gate and the bay. If the terminal also handles LPG, read [LPG terminal automation](https://citia-engineering.com/en/knowledge/lpg-terminal-automation), because weighing and gas safety change the boundaries. The article on [TAS, TMS and SAP integration](https://citia-engineering.com/en/knowledge/tas-tms-sap-integration) covers the enterprise side in more detail.

## Terms used in this guide

- TBBM: Terminal Bahan Bakar Minyak: a fuel terminal that receives, stores and distributes fuel.
- TAS: Terminal automation system: runs orders, gates, loading and documents.
- TMS: Tank management system: turns gauge readings into tank stock and tank tickets.
- Batch controller: Bay device that loads a preset quantity through a meter and valve.
- Permissive: A condition that must be true before loading may start, such as a good earth connection.
- FDS: Functional design specification: how the system behaves, step by step.
- FAT, SAT, SIT: Factory, site and site integration acceptance tests.
- Cutover: The planned switch from the old way of working to the new system.

## Frequently asked questions

Q: What is a fuel terminal automation system?

A: It is the combination of field instruments, controllers and software that runs receipt, storage and truck loading at a fuel terminal and records every quantity from the measuring devices. In Indonesia it usually means a TAS for loading and a TMS for tanks, both connected to SAP.

Q: How does a terminal automation system work?

A: It checks each step of a truck visit against the one before: order from SAP, gate-in, bay assignment, permissives, preset loading, sealing and gate-out. Results go back to SAP automatically, so the delivery note and the meter reading are the same record.

Q: What are the main components of a TAS?

A: The main components are field devices (meters, valves, RFID readers, grounding units), controllers (PLCs and batch controllers), the TAS and TMS applications with SCADA, and the link to SAP. Each layer should keep its safety functions working when the layer above fails.

Q: Does a TBBM have to report stock data to BPH Migas?

A: Yes, fuel trading licence holders must report operational reserves per storage facility under Peraturan BPH Migas 9/2020. The daily records are submitted every month by the 20th of the following month, through a channel integrated with the BPH Migas information system.

Q: What should be prepared before implementing a TAS?

A: Prepare a device list with protocols, the tera status of meters and tanks, the SAP interface list, the network layout and a cutover plan per bay. These decide the design and the schedule more than the choice of software.

Q: Can a TAS be installed while the terminal keeps operating?

A: Yes, most projects at running terminals switch over bay by bay, with each bay tested before it returns to service. The cutover plan has to be agreed with operations, because some bays are out of service during their switch.

## Sources and further reading

1. Peraturan Badan Pengatur Hilir Minyak dan Gas Bumi Nomor 9 Tahun 2020 tentang Penyediaan Cadangan Operasional Bahan Bakar Minyak (BN 2020 No. 1789), BPH Migas, Berita Negara Republik Indonesia, 2020 (https://www.peraturan.go.id/files/bn1789-2020.pdf)
2. Peraturan Menteri Perdagangan Nomor 24 Tahun 2024 tentang Kegiatan Tera dan Tera Ulang Alat Ukur, Alat Takar, Alat Timbang, dan Alat Perlengkapan Metrologi Legal, Kementerian Perdagangan, 2024-10-04 (https://peraturan.go.id/filespengundangan/permendag-no-24-tahun-2024.pdf)
3. Undang-Undang Nomor 2 Tahun 1981 tentang Metrologi Legal, Pemerintah Republik Indonesia, 1981 (https://peraturan.go.id/files/uu2-1981.pdf)
4. OIML R 117-1:2019 Dynamic measuring systems for liquids other than water, Part 1, International Organization of Legal Metrology (OIML), 2019 (https://www.oiml.org/en/files/pdf_r/r117-1-e19.pdf)
5. API MPMS Chapter 6.2A: Metering Assemblies, Truck and Rail Loading and Unloading Measurement Systems, American Petroleum Institute (listing by BSI), 2021 (https://knowledge.bsigroup.com/products/metering-assemblies-truck-and-rail-loading-and-unloading-measurement-systems)
6. IEC 62381:2024 Automation systems in the process industry: FAT, SAT and SIT, International Electrotechnical Commission (IEC), 2024 (https://webstore.iec.ch/en/publication/67572)
7. IEC 60079-0 Explosive atmospheres, Part 0: Equipment, general requirements, International Electrotechnical Commission (IEC) (https://webstore.iec.ch/en/publication/620)
8. ISA/IEC 62443 Series of Standards, International Society of Automation (ISA) (https://www.isa.org/standards-and-publications/isa-standards/isa-iec-62443-series-of-standards)
9. NFPA 77 Recommended Practice on Static Electricity, National Fire Protection Association (NFPA) (https://www.nfpa.org/codes-and-standards/nfpa-77-standard-development/77)
10. ISA-95 Standard: Enterprise-Control System Integration, International Society of Automation (ISA) (https://www.isa.org/standards-and-publications/isa-standards/isa-95-standard)
11. Fuel Terminal Jambi distribution workflow, PT Citia Engineering Indonesia, 2026 (https://citia-engineering.com/en/projects/jambi-terminal-automation)

Preparing a TAS or TMS project at a fuel terminal?: Send siTia your device list or a short description of the terminal, and the engineering team will help you sort out the scope.

## Contact

- Company: PT Citia Engineering Indonesia
- siTia - Virtual Assistance: [WhatsApp +62 813-2206-507](https://wa.me/628132206507). siTia answers questions about our products, projects and enquiries on WhatsApp. Replies are automated, and a person from the Citia team follows up.
- Email: services@citia-engineering.com
- Phone / WhatsApp (siTia): +62 813-2206-507
- Location: Bandung, Indonesia

[Contact Citia](https://citia-engineering.com/en/contact.md)

## Structured data (JSON-LD)

```json
{
  "@context": "https://schema.org",
  "@graph": [
    {
      "@type": "Organization",
      "@id": "https://citia-engineering.com/#organization",
      "name": "Citia Engineering Indonesia",
      "legalName": "PT Citia Engineering Indonesia",
      "alternateName": "Citia",
      "url": "https://citia-engineering.com",
      "logo": {
        "@type": "ImageObject",
        "url": "https://citia-engineering.com/media/citia-logo.png",
        "width": 950,
        "height": 328
      },
      "description": "Citia is an engineering and system integration company in Bandung, Indonesia. We connect field devices, PLC and SCADA, terminal software and enterprise systems, then install, test and maintain them.",
      "email": "services@citia-engineering.com",
      "telephone": "+62 813-2206-507",
      "address": {
        "@type": "PostalAddress",
        "addressLocality": "Bandung",
        "addressRegion": "Jawa Barat",
        "addressCountry": "ID"
      },
      "contactPoint": [
        {
          "@type": "ContactPoint",
          "contactType": "customer service",
          "email": "services@citia-engineering.com",
          "telephone": "+62 813-2206-507",
          "url": "https://citia-engineering.com/en/contact"
        },
        {
          "@type": "ContactPoint",
          "contactType": "customer support",
          "name": "siTia - Virtual Assistance",
          "telephone": "+62 813-2206-507",
          "url": "https://wa.me/628132206507",
          "areaServed": "ID",
          "availableLanguage": [
            "id",
            "en"
          ]
        }
      ],
      "areaServed": {
        "@type": "Country",
        "name": "Indonesia"
      },
      "slogan": "Bridging Ideas into Reality",
      "publishingPrinciples": "https://citia-engineering.com/en/editorial-policy",
      "foundingDate": "2020-01-17",
      "foundingLocation": {
        "@type": "Place",
        "name": "Bandung, Indonesia",
        "address": {
          "@type": "PostalAddress",
          "addressLocality": "Bandung",
          "addressRegion": "Jawa Barat",
          "addressCountry": "ID"
        }
      },
      "knowsAbout": [
        "Terminal automation system",
        "Automatic tank gauging",
        "Tank management system",
        "SCADA",
        "Programmable logic controller",
        "Modbus",
        "Field instrumentation",
        "Weighbridge",
        "Pipeline pressure monitoring",
        "Industrial IoT"
      ],
      "brand": [
        {
          "@type": "Brand",
          "@id": "https://citia-engineering.com/#brand-integra",
          "name": "INTEGRA"
        },
        {
          "@type": "Brand",
          "@id": "https://citia-engineering.com/#brand-catalyst",
          "name": "CATALYST"
        }
      ],
      "sameAs": [
        "https://www.linkedin.com/company/citia-engineering-indonesia/",
        "https://www.youtube.com/@citiaengineering",
        "https://www.facebook.com/citiaengineering/",
        "https://www.instagram.com/citiaengineering/"
      ]
    },
    {
      "@type": "WebSite",
      "@id": "https://citia-engineering.com/#website",
      "url": "https://citia-engineering.com",
      "name": "Citia Engineering Indonesia",
      "inLanguage": [
        "en",
        "id"
      ],
      "publisher": {
        "@id": "https://citia-engineering.com/#organization"
      },
      "potentialAction": [
        {
          "@type": "SearchAction",
          "name": "Search Citia News",
          "target": {
            "@type": "EntryPoint",
            "urlTemplate": "https://citia-engineering.com/en/news?q={search_term_string}"
          },
          "query-input": "required name=search_term_string"
        },
        {
          "@type": "SearchAction",
          "name": "Cari di News Citia",
          "target": {
            "@type": "EntryPoint",
            "urlTemplate": "https://citia-engineering.com/id/news?q={search_term_string}"
          },
          "query-input": "required name=search_term_string"
        }
      ]
    },
    {
      "@type": "WebPage",
      "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#webpage",
      "url": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide",
      "name": "Fuel terminal automation in Indonesia: how it works and how to prepare an implementation",
      "description": "A fuel terminal automation system runs TBBM loading and stock from order to posting. Learn how it works, its components and what to prepare to implement it.",
      "inLanguage": "en",
      "isPartOf": {
        "@id": "https://citia-engineering.com/#website"
      },
      "publisher": {
        "@id": "https://citia-engineering.com/#organization"
      },
      "about": {
        "@id": "https://citia-engineering.com/#organization"
      },
      "breadcrumb": {
        "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#breadcrumb"
      },
      "datePublished": "2026-11-18",
      "dateModified": "2026-11-18",
      "speakable": {
        "@type": "SpeakableSpecification",
        "cssSelector": [
          "h1",
          ".lead"
        ]
      },
      "mainEntity": {
        "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#entity"
      }
    },
    {
      "@type": "BreadcrumbList",
      "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#breadcrumb",
      "itemListElement": [
        {
          "@type": "ListItem",
          "position": 1,
          "name": "Citia",
          "item": "https://citia-engineering.com/en"
        },
        {
          "@type": "ListItem",
          "position": 2,
          "name": "Knowledge",
          "item": "https://citia-engineering.com/en/knowledge"
        },
        {
          "@type": "ListItem",
          "position": 3,
          "name": "Fuel terminal automation in Indonesia: how it works and how to prepare an implementation",
          "item": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide"
        }
      ]
    },
    {
      "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#entity",
      "url": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide",
      "mainEntityOfPage": {
        "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#webpage"
      },
      "@type": "TechArticle",
      "headline": "Fuel terminal automation in Indonesia: how it works and how to prepare an implementation",
      "description": "How a fuel terminal automation system runs a TBBM day to day, which components sit in each layer, which Indonesian rules shape the design, and what to prepare before an implementation starts.",
      "datePublished": "2026-11-18",
      "dateModified": "2026-11-18",
      "author": {
        "@id": "https://citia-engineering.com/#organization"
      },
      "publisher": {
        "@id": "https://citia-engineering.com/#organization"
      },
      "publishingPrinciples": "https://citia-engineering.com/en/editorial-policy",
      "inLanguage": "en",
      "articleSection": "Terminal Operations",
      "image": "https://citia-engineering.com/media/field/wide-padalarang-tas-gantry-02-1024.webp"
    },
    {
      "@type": "FAQPage",
      "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#faq",
      "url": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide",
      "inLanguage": "en",
      "isPartOf": {
        "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#webpage"
      },
      "mainEntity": [
        {
          "@type": "Question",
          "name": "What is a fuel terminal automation system?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "It is the combination of field instruments, controllers and software that runs receipt, storage and truck loading at a fuel terminal and records every quantity from the measuring devices. In Indonesia it usually means a TAS for loading and a TMS for tanks, both connected to SAP."
          }
        },
        {
          "@type": "Question",
          "name": "How does a terminal automation system work?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "It checks each step of a truck visit against the one before: order from SAP, gate-in, bay assignment, permissives, preset loading, sealing and gate-out. Results go back to SAP automatically, so the delivery note and the meter reading are the same record."
          }
        },
        {
          "@type": "Question",
          "name": "What are the main components of a TAS?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "The main components are field devices (meters, valves, RFID readers, grounding units), controllers (PLCs and batch controllers), the TAS and TMS applications with SCADA, and the link to SAP. Each layer should keep its safety functions working when the layer above fails."
          }
        },
        {
          "@type": "Question",
          "name": "Does a TBBM have to report stock data to BPH Migas?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "Yes, fuel trading licence holders must report operational reserves per storage facility under Peraturan BPH Migas 9/2020. The daily records are submitted every month by the 20th of the following month, through a channel integrated with the BPH Migas information system."
          }
        },
        {
          "@type": "Question",
          "name": "What should be prepared before implementing a TAS?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "Prepare a device list with protocols, the tera status of meters and tanks, the SAP interface list, the network layout and a cutover plan per bay. These decide the design and the schedule more than the choice of software."
          }
        },
        {
          "@type": "Question",
          "name": "Can a TAS be installed while the terminal keeps operating?",
          "acceptedAnswer": {
            "@type": "Answer",
            "text": "Yes, most projects at running terminals switch over bay by bay, with each bay tested before it returns to service. The cutover plan has to be agreed with operations, because some bays are out of service during their switch."
          }
        }
      ]
    },
    {
      "@type": "DefinedTermSet",
      "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary",
      "url": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide",
      "inLanguage": "en",
      "isPartOf": {
        "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#webpage"
      },
      "name": "Terms used in this guide",
      "hasDefinedTerm": [
        {
          "@type": "DefinedTerm",
          "name": "TBBM",
          "description": "Terminal Bahan Bakar Minyak: a fuel terminal that receives, stores and distributes fuel.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "TAS",
          "description": "Terminal automation system: runs orders, gates, loading and documents.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "TMS",
          "description": "Tank management system: turns gauge readings into tank stock and tank tickets.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "Batch controller",
          "description": "Bay device that loads a preset quantity through a meter and valve.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "Permissive",
          "description": "A condition that must be true before loading may start, such as a good earth connection.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "FDS",
          "description": "Functional design specification: how the system behaves, step by step.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "FAT, SAT, SIT",
          "description": "Factory, site and site integration acceptance tests.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        },
        {
          "@type": "DefinedTerm",
          "name": "Cutover",
          "description": "The planned switch from the old way of working to the new system.",
          "inDefinedTermSet": {
            "@id": "https://citia-engineering.com/en/knowledge/fuel-terminal-automation-guide#glossary"
          }
        }
      ]
    }
  ]
}
```